Amtrak ta ce jirage sun koma aiki bayan aikin gini na musamman a First Street Tunnel, kudancin Washington Union Station. Sanarwarta ta 26 ga Oktoba ta ruwaito kammala aikin Pause for Progress na kwana tara, wanda ya buƙaci sauye-sauyen tafiya zuwa kudu daga babban birni.
Aikin ya mayar da hankali kan A-Interlocking, wurin layi da sarrafawa da jiragen Amtrak da Virginia Railway Express ke amfani da shi tsakanin Washington da Virginia. Sabis daban suna raba wannan kayan aiki, kodayake fasinjojinsu suna da wuraren farawa da ƙarewa daban.
Ma'aikata sun sauya makunnin layi da hanyoyin ketarawa, sun gyara tushen layin ramin, sannan suka sanya tsarin sarrafa makunnin lantarki. Waɗannan sauye-sauye ne na kayan aiki da tsarin layi da ke taimaka wa motsin jirage. Amtrak ta bayyana su a matsayin jari na inganta dogaro da sabis.
Kamfanin ya tsara katsewar tare da VRE, Virginia Passenger Rail Authority da ma'aikatar sufuri ta North Carolina. Ya kuma gode wa layukan jigilar kaya da hukumar sufuri ta Washington. Gudanar da rufewar ya shafi hanyar sadarwa mai faɗi, ba ramin kaɗai ba.
Sanarwar ta bayyana sauyin sabis tsakanin 16 da 26 ga Oktoba. Ta kuma ce wasu motocin express-bus da aka fara domin aikin za su ci gaba a lokacin hutu. Hakan ya nuna cewa wani ɓangaren martanin sufuri zai iya wuce lokacin aikin gini.
Babban matakin da aka ruwaito shi ne kammala wannan aikin da aka tsara da komawar jirage a lokacin. Ba tabbacin cewa wata matsala daban ba za ta shafi jirgi nan gaba ba ne. Matafiya su fahimci sanarwar a matsayin bayanin kayayyakin more rayuwa, tare da duba bayanin tafiyarsu na takamaiman rana.